Phase | Effort and Size | Schedule | ||
---|---|---|---|---|
Optimisitic | Pessimisitc | Optimisitic | Pessimisitc | |
Initial product concept | 0.25 | 4.0 | 0.60 | 1.60 |
Approved product concept | 0.50 | 2.0 | 0.80 | 1.25 |
Requirements specification | 0.67 | 1.5 | 0.85 | 1.15 |
Product design specification | 0.80 | 1.25 | 0.90 | 1.10 |
Detailed design specification | 0.90 | 1.10 | 0.95 | 1.05 |
< Source : Adapted from "Cost Models for Future Software Life Cycle Processes : COCOMO 2.0" (Boehm et al. 1995) >